Construction Projects

The Township determines future road construction projects by reviewing known problems, location and underground services and comparing to available funding.  Council gives final approval during the budget process. Information about current Bids and Tenders can be found online.

Bridge Repairs

  • The Township of Centre Wellington has begun repairing various bridges from September 3 to October 31, 2019
  • The bridges to be repaired are in three locations, 1 in former Pilkington Township and 2 in former Nichol Township in Centre Wellington. Details of the work are as follows:
    • Beatty Line between Sideroad 10 N and Sideroad 10 S, concrete deck repairs to structure #3-N
    • Second Line between Wellington Road 7 and Sideroad 6 N, concrete repairs to structure #13-N
    • First Line between Wellington Road 17 and Sideroad 11, concrete repairs to structure #29-P
  • The contractor for this project is Xterra Construction Limited, Kitchener, Ontario

Eramosa/Garafraxa Townline, former West Garafraxa Township

  • The Township of Centre Wellington will be rebuilding Eramosa/Garafraxa Townline between Sixth Line (West Garafraxa) and Wellington Road 26 in the former Township of West Garafraxa. The construction will begin August 2019 and it is anticipated to be completed mid-September 2019.
  • The road will continue to be closed to through traffic during the construction period. Local access will be maintained with interruptions at various times during this period.
  • Construction will be completed by the Township's Road Department.
  • This project is partially funded by the Association of Municipalties Ontario, Federal Gax Tax Fund. For more on how this program works, visit the gas tax at work website or https://youtu.be/SNWcoXSyxjI

Garafraxa Street E and Gartshore Street, Fergus

  • The Township of Centre Wellington began construction of municipal services and sidewalk on Garafraxa Street E (between Gartshore Street and Tom Street), Fergus May 27 2019.
  • Beginning in summer 2019 is a new section of sidewalk on Gartshore Street (between Garafraxa Street E and Middleton Avenue)
  • The contractor for this project is Drexler Construction Ltd., Rockwood, Ontario

Inverhaugh Storm Outlet Wellington Road 21, former Pilkington Township

  • The Township of Centre Wellington began construction of storm outlet on Wellington Road 21 and Sideroad 4, Pilkington July 29 2019. The construction is anticipated to be completed by the end of August 2019.
  • The road will be open to through traffic during the construction period with periodic traffic interruptions.
  • The contractor for this project is Drexler Construction Ltd., Rockwood, Ontario

Metcalfe Street- Badley Bridge Replacement (County of Wellington Project)

  • Wellington County is planning to replace the Badley Bridge over the Grand River on Metcalfe Street starting in late 2019
  • For more information, please visit the County's road webpage for additional bridge details.

Replacement of Bridge 10-P Fourth Line E, Former Pilkington Township

  • The Township of Centre Wellington is proceeding with the replacement of structure 10-P, Fourth Line E, former Pilkington Township. The construction is to commence Summer 2019 and will be completed by the end of the year.
  • Fourth Line E between Sideroad 10 and Sideroad 14 will continue to be closed to through traffic during the construction period. Local access will be maintained with interruptions at various times during this period.
  • The contractor for this project is Esposito Bros. Ltd., Bolton, Ontario

Sideroad 5, former Pilkington Township

  • The Township of Centre Wellington will be rebuilding 300 metres of Sideroad 5 between Third Line West and First Line West in the former Pilkington Township. The construction will begin and be completed Summer 2019.
  • The road will continue to be closed to through traffic during the construction period. Local access will be maintained with interruptions at various times during this period.
  • Construction is being completed by the Township's Road Department.

St. Andrew Street East and Tom Street, Fergus

  • The Township of Centre Wellington began the reconstruction of St. Andrew Street East (between Gartshore Street and Lamond Street) and Tom Street, Fergus in April 2018. The project restarted in May 2019 to complete all outstanding landscaping and construction deficiencies.  
  • The contractor for this project is Drexler Construction Ltd., Rockwood, Ontario.
  • A Public Open House to discuss the project details was held on Wednesday, March 14, 2018 at the Fergus Sportsplex.  ​

St. David Street Bridge (Highway No. 6), Fergus

The St. David Street Bridge has been re-opened

  • Bell has begun their work at the intersection of St. Andrew St. / St. David St. and at the intersection of Bridge St. / St. David St. to pull their wiring beneath the bridge for the conversion of their overhead lines to underground.  Once the underground wiring is installed they will also need to remove their utility pole and guywires.  We anticipate that there may be some traffic disruptions or temporary periodic traffic interruptions for the Bell work,  but that Northbound and Southbound traffic will generally be maintained across the bridge and through the adjacent intersections during the Bell work.
  •  Once the Bell pole and guywires are removed in front of the Old Livery building, the bridge contractor will pour the concrete slab in this area as well as the slab in front of the Brewhouse

Combined Detour Map for vehicles and heavy trucks

St. David Street Bridge Drawings

St. David Street Bridge Rendering Drawing

St. David Street Bridge Display Board 

St. David Street Bridge Signage Display Board

St. David Street North (Highway No. 6) and Gordon Street, Fergus

  • The Township of Centre Wellington began the reconstruction of St David Street North and Gordon Street, Fergus in June 2019 and will be completed by the end of Summer 2019.
  • Both St David Street North and Gordon Street will remain open during construction with lane restrictions and traffic interruptions at various times during this period. 
  • The contractor for this project is Drexler Construction Ltd., Rockwood, Ontario.

Tower Street, Fergus Intersection Improvements

  • The Township of Centre Wellington will be proceeding with construction of the North bound right turn lane on Tower Street, Fergus on September 9, 2019 and will continue to October 2019.
  • Tower Street (Highway 6) northbound traffic will be detoured. Union Street West between Tower Street and Angus Street will be closed to through traffic during the construction period and local access will be interrupted at various times. 
  • The contractor for this project is Steed and Evans Limited, St. Jacobs, Ontario.

Township Paving

  • The Township of Centre Wellington began paving various roads May 27 2019 and will continue to Fall 2019.
  • There are various streets in Fergus, Elora and Rural Centre Wellington that are to be repaved.
  • The West Garafraxa/Eramosa Townline from Wellington Road 21 to the Third Line is partially funded by the Association of Municipalities Ontario, Federal Gas Tax Fund. For more information on how this program works, visit the gas tax at work website or https://youtu.be/SNWcoXSyxjI
  • The contractor for this project is The Murray Group Limited, Moorefield, Ontario

Victoria Street Pedestrian Bridge, Elora

  • The Township of Centre Wellington has begun construction of a new pedestrian bridge between Carlton Place and West Mill Street, Elora August 2018. The project is expected to be completed by Fall 2019.
  • West Mill Street will be closed to through traffic at times during the construction period and local access will be interrupted at various times. The Carlton Place parking lot will be partially occupied by the construction activity.
  • The Contractor for this project is Bronte Construction, Oakville, Ontario.
  • A public consultation meeting followed by a special council meeting was held at the Elora Community Centre on November 22, 2017.
  • More information can be found on CW Connect.

Woolwich Street and Geddes Street Watermain Extension/ Salem Bridge (With County of Wellington)

  • Wellington County will begin construction to replace the Salem Bridge over the Irvine Creek at Woolwich St May 14 2019. The project will also include improvements to the layout of the intersections at Geddes Street and James Street.  Construction is anticipated to be completed by the end of December 2019.
  • The Township of Centre Wellington will be completing the extension of the watermain starting at the intersection of Geddes Street and Avruskin Street. It will extend north along Geddes Street and then west along Woolwich Street to Ann Street. The existing sidewalks will also be replaced with new sidewalks constructed along the north side of Woolwich Street starting at Ann Street and along the east side of Geddes Street to Avruskin Street.
  • Wellington Road 18 (Woolwich/Geddes St) will be closed to through traffic during the construction period and local access will be interrupted at various times.
  • The contractor for this project is McLean Taylor Construction Ltd., St. Marys, Ontario
  • A public open house was held on February 13, 2019 at the Elora Community Centre where preliminary drawings were on display.

York Street and High Street, Elora

  • The Township of Centre Wellington began reconstruction of York Street between High Street and Waterloo St, Elora as well as High Street between McNab Street and York Street that started on April 29, 2019. Construction is anticipated to be completed by the end of Fall 2019.
  • The street will be closed to through traffic during the construction period and local access will be interrupted at various times.
  • This project is partially funded by the Association of Municipalties Ontario, Federal Gax Tax Fund. For more on how this program works, visit the gas tax at work website or https://youtu.be/SNWcoXSyxjI
  • The contractor for this project is Goetz Construction, Guelph, Ontario
  • A Public Open House was held on December 13, 2018 in Veteran's Hall from 6:00-7:30pm

Contact Us

Township of Centre Wellington
1 MacDonald Square, Elora, Ontario, Canada, N0B 1S0
Phone: 519.846.9691
Email Us
Map this location